NYI Status

Maintenance (NYIIX) notification from Hopone

by K.Pha@NYI on Jan.12, 2010, under Uncategorized

Greetings,

Our circuit provider Level3 will perform maintenance on the circuit connected to our router at NYIIX. The maintenance window is scheduled on Thursday, January 21, 2010 from 00:00 ET to 06:00 ET. During the maintenance window, our bgp peering session with our peers at NYIIX will be down for up to 5 minutes.

Our network info at NYIIX:

IP: 198.32.160.96
ASN: 14361

We apologize for any inconvevience this may bring to you and thank you for your understanding.

Regards,

Weibo Deng
Network Engineer
1-206-438-5900×4109
Hopone Internet Corp. AS 14361 - www.hopone.net
“The Foundation of Internet Success.”(R)

Leave a Comment :, , more...

Scheduled Maintenance: LGA5 12/11/09, 00:01 - 02:00 EST

by K.Pha@NYI on Dec.04, 2009, under Uncategorized

Dear AboveNet Customer,

AboveNet is planning scheduled hardware maintenance. The details of this maintenance are below.

Date & Time: 12/11/09, 00:01 - 02:00 EST

Location(s): LGA5

Description: AboveNet will be performing a power maintenance on mpr1.lga5.us.

Customer Impact: AboveNet does not anticipate any disruption to your service terminated on mpr1.lga5.us.

Leave a Comment more...

Scheduled Maintenance at 25 Broadway

by K.Pha@NYI on Dec.01, 2009, under Uncategorized

UPDATE: Telehouse has again reschedule this maintenance window to Saturday, January 30th starting at 9:00pm and ending 10:00pm.

UPDATE: Telehouse has rescheduled this maintenance to Saturday, December 19th, 9PM - 10PM.

Telehouse has scheduled a maintenance at 25 Broadway on;

Date: Thursday, December 17th starting at 9:00pm and lasting until 10:00pm.

This is to improve reliability of our air conditioning system. We need to shut down all CRAC units on the 6th floor . We will do everything to stabilize the room temperature. We expect no service impact with this work.
Please feel free to contact me for any questions concerning this Preventative Maintenance.

Regards,

Michael Florio
Facilities Manager,
Facilities Engineering & Operations
TELEHOUSE International Corporation of America
7 Teleport Drive
Staten Island, NY 10311
Voice: 718-355-2530

Leave a Comment : more...

Floor Cleaning at NY1

by K.Pha@NYI on Nov.12, 2009, under Uncategorized

A floor cleaning and under-floor cleaning will begin in data center NY1 at 9AM on Wednesday, November 18th.

Leave a Comment :, more...

Phone Lines Down

by K.Pha@NYI on Nov.11, 2009, under Talk to NYI

We are currently unable to receive phone calls, and are working with our phone service provider to correct the situation.  If you need to contact NYI, please be sure to create a ticket at https://my.nyi.net If you do not already have a HelpDesk username, you can click on the ‘Sign Up’ button at https://my.nyi.net in order to create one.
UPDATE: Phone service has been restored.

1 Comment : more...

25 Broadway maintenance on November 5th

by K.Pha@NYI on Oct.28, 2009, under Uncategorized

To our valued customers at Telehouse,

Telehouse would like to inform you that we will be cancelling replacing fuse
block on dry cooler pump starters at 25 Broadway on November 5th at 8:00pm.
I will update with a revised date when received. Any questions please feel
free to call.

Thanks,

Michael Florio
Facilities Manager,
Facilities Engineering & Operations
TELEHOUSE International Corporation of America
7 Teleport Drive
Staten Island, NY 10311
Voice: 718-355-2530
Fax: 718-355-2517
Leave a Comment :, , more...

Notification of BGP session outage at NYIIX from Hopone

by K.Pha@NYI on Oct.27, 2009, under Email, Uncategorized

Dear peer at NYIIX,

Our circuit provider Level3 will perform a maintenance on out circuit to the peering place NYIIX at New York, from 00:00 ET to 06:00 ET, Thursday, October 29, 2009 (and a  back up maintenance window is also scheduled for this from 00:00 ET to 06:00 ET, Saturday, October 31, 2009 in case the work is not completed in the previous window). During the window, you will experience bgp outage with us for up to 1 hour. We apologize for any inconvenience this may bring to you and thank you for your understanding.
Best regards,

Weibo Deng
Network Engineer
1-206-438-5900×4105
Hopone Internet Corp. AS 14361 - www.hopone.net
“The Foundation of Internet Success.”(R)
Leave a Comment :, , , , more...

Building Power Infrastructure Maintenance

by K.Pha@NYI on Oct.05, 2009, under Facilities Maintenance

We have just been informed that on the morning of Saturday, October 10th, building engineers will be performing maintenance on the power infrastructure at 100 William Street. We do not expect to lose power to any of our facilities in the building, but will have our generators on stand-by as a precaution. In order to prevent and if necessary deal with any issues that may arise during this period, we will have engineers from our generator maintenance vendor on call, as well as electricians and extra technical support staff.

2 Comments :, , more...

RCN Maintenance

by K.Pha@NYI on Oct.05, 2009, under Uncategorized

Sometime between the hours of 11 PM on 2009-11-07 and 6 AM 2009-11-08, RCN will be performing a software upgrade on an optical digital cross connect device, which could effect circuits entering 100 William Street.  We have been informed that no NYI-related circuits will be impacted.

Leave a Comment : more...

Biometric Scanner Unit Replaced

by K.Pha@NYI on Jul.30, 2009, under Facilities Maintenance

The biometric scanner unit providing access into the main room of datacenter NY1 (21st floor of our 100 William Street location) has been replaced. Those clients who were experiencing sluggish fingerprint scans and other issues when attempting to gain access via that scanner are asked to let us know if you see any further issues.

Leave a Comment :, , more...

Looking for something?

Use the form below to search the site:

Still not finding what you're looking for? Drop a comment on a post or contact us so we can take care of it!

Visit our friends!

A few highly recommended friends...